Friday, October 10, 2008

Are we Permitted?

After months, and I do mean months, of awaiting approval from the county planning commission, at last our wind turbine has recieved all of its permits.

That date was 25 September 08 and you can see what day it is today.

Our hole was properly dug in half a day by Keith, our amazing excavator, on 6 Oct, after the gang from GridFeeders came out and plotted out the exact location. on the Friday beforehand. It's still a great big hole. We're still awaiting the contractor to frame in the concrete and then we can pour.

The wind is blowing hard. There's just no Las Vegas ding to it. No turbine in the air yet. Gridfeeders has as much as I do invested; this is their first pivate wind turbine in this county. Hurry! Hurry!

Being first is very difficult.